The City of High Point will perform improvements in the areas listed below. Due to the nature of the construction work, some streets may be closed and you should expect the use of heavy construction equipment. Our intentions are to manage the project in a manner that will minimize inconveniences. Your patience and understanding during this construction process will be much appreciated.
These dates are estimates. Actual dates are dependent upon weather conditions.
Corbett Outfall Section A & B,
October 1, 2002 through December 31, 2008 (estimated)
City Contact: Greg Hall, Project Engineer - 336-883-3166
Davis-Martin-Powell & Associates 336-886-4821
TBD
Will be paid by Revenue Bonds
All applicable permits were applied for in January 2006. Permit from NCDOT is pending. Plans are complete and easements are being acquired. Construction of this project is to begin in the Fall of 2007. Plans complete. Most easement acquired, one relocation being considered. DWQ Sewer, 401, COE, Land Quality Permits approved. Coordinate construction schedule with Kool Pool project. (MAP LINK) Estimated project duration includes design and construction processes.
Kindergarden Outfall Section 1A,
October 1, 2002 through February 28, 2009 (estimated)
City Contact: Greg Hall, Project Engineer - 336-883-3166
Davis-Martin-Powell & Associates 336-886-4821
TBD
Will be paid by Revenue Bonds
The city has applied for all applicable permits. Permit from NCDOT is pending. Plans are completed and easement must be acquired. Construction is scheduled to begin in the Spring of 2008. Plans completed. Easement info submitted to R/W Agent & Alignment staked. DWQ Sewer, Land Quality, 401, COE Permits approved. Coordinate construction schedule with Kool Pool project. (MAP LINK) Estimated project duration includes design and construction processes.