BE IT RESOLVED by the City Council of the City of High Point, North Carolina that pursuant to the provisions of NCGS 160A-414 and Section 9-3-20 of the High Point Development Ordinance, the City Council hereby establishes the following schedule of fees pertaining to planning, development and inspection services.
Planning & Development Department
Effective September 1, 2003
Schedule I
Development Application, Subdivision & Site Plan Review Fees
Schedule I pertains to fees associated with the review of development applications, subdivisions and site plans. These fees are intended to defray the cost of legal advertisement, public notice, material and other operational costs the city incurs with processing these application and plan requests.
All application, subdivision and plan review fees are payable at the time of submission of the application or plan. In accordance with the city's Development Ordinance, no action shall be taken on proceedings before the Board of Adjustment, Planning and Zoning Commission, Historic Preservation Commission, Technical Review Committee or Watershed Review Committee until all applicable fees have been paid in full. There shall be no refund of a fee, except as provided specifically herein. A fee shall not be required if the application or plan is submitted by the City Council, any city board, commission or department.
|
Subdivision and Plan Review Fees | |
|
Subdivision | |
|
Sketch Plan |
No charge |
|
Preliminary Plat |
$100 + $20 per lot |
|
Final Plat |
$ 50 per plat |
|
Site Plan | |
|
Including IMUDs, Group |
$100 |
|
Developments, and Recreational Vehicle Parks. |
+ $4 per dwelling unit or space |
|
Street & Utility Construction Plan | |
|
-For street, water, sanitary sewer and storm sewer facilities |
$ 50 per submittal |
|
Watershed Development Plan |
$100 + $25 per control device |
|
ISA review only |
$ 25 |
|
PUD Unified Development Plan |
$200 (if reviewed separately) |
|
TND Master Plan |
$200 (if reviewed separately) |
|
$ 75 | |
|
$100 | |
|
Exclusion Map |
$ 50 |
|
Plat or Plan Minor Revision | |
|
For valid approvals or conditional approvals. |
$ 25 + increased or additional per lot, dwelling unit, space, square footage, or control device fee |
Schedule II
Public Regional Stormwater Facility Fees
|
Impervious Surface Area (ISA) of Site Treated by Public Regional Stormwater Facility |
Cost Per Impervious Surface Area (ISA) Acre |
|
Minimum Fee |
$ 2,000 |
|
0-1 ISA acre |
$ 0.35 per ISA square foot |
|
>1-5 ISA acres |
$ 30,000 per ISA acre |
|
>5-10 ISA acres |
$150,000 + $15,000 per ISA acre over 5 |
|
>10 ISA acres |
$225,000 + $ 9,000 per ISA acre over 10 |
|
Fee Application Outside Corporate Limits |
For property outside the corporate limits, the cost per impervious surface area acre shall be 100% greater. |
|
Fee Application to Streets |
The stormwater facility fee applies to all impervious surface within a development, including public and private streets; however, where a developer constructs a 4-lane or larger public street within a development, then the fee shall apply to only 50% of the impervious surface area of that public street. |
|
City Property |
A fee shall not be charged to any city owned property utilizing a public regional stormwater facility. |
|
Fee Refund |
No refunds shall be made unless the applicable watershed development plan is voided or revised accordingly and no impervious surface has been installed. |
Schedule III
General Permit & Inspection Fees
Schedules III through VIII pertain to fees associated with the review, permitting and inspection of building construction, structures and land uses. These fees are intended to offset the city's cost for administering and operating the inspections program.
Upon the request of the permit holder, an 80% refund may be authorized where no field inspections or other inspection work has been conducted, provided, that a minimum of $40.00 shall be retained.
|
Minimum Permit or Inspection Fee:
|
$ 40.00 |
|
Modular Construction:
|
$120.00 |
|
Manufactured Housing:
|
$ 70.00 |
|
Building Demolition: | |
|
$ 40.00 |
|
$120.00 |
|
Building Relocation:
|
|
|
Construction Plan Review: | |
|
$ 50.00 |
|
|
|
$ 75.00 |
|
$125.00 |
|
Plan Revision:
|
$ 40.00 |
|
Occupant Load Posting:
|
$ 40.00 |
|
Stocking Inspection:
|
$ 50.00 |
|
Temporary Certificate of Compliance:
|
$100.00 |
|
$ 75.00 |
|
Beverage Licenses and Privilege Licenses:
|
$ 60.00 |
|
Commercial Fire Prevention Review: | |
|
$ 40.00 |
|
$ 40.00 |
|
$ 40.00 |
|
Re-inspection Fees: | |
|
1st Re-inspection |
$ 40.00 |
|
Additional re-inspection |
$ 60.00 |
|
Working Without A Permit:
|
2 x permit fee |
|
Failure To Obtain Final Inspection:
|
$100.00 |
Schedule V
Building Permit Fees
|
For the purposes of calculating building permit fees, the building construction value shall be determined based upon the finished and unfinished square footage under roof using the construction cost information listed in the most recent version of the Building Valuation Data published by Southern Building Code Congress International (SBCCI). |
|
Building permits are required on all construction unless exempted by N.C. General Statute 160A-417 as follows:
|
|
On "Fast Track" or other projects, where incremental permits are issued, fees shall be calculated at 110% of the normal fee. |
|
Construction Value |
Permit Fee |
|
$ 1 to $ 9,000 |
$ 40.00 |
|
$ 10,000 to $ 49,000 |
$ 40.00 + $4.00/1,000 or fraction thereof over 9,000 |
|
$ 50,000 to $ 99,000 |
$ 200.00 + $3.00/1,000 or fraction thereof over 49,000 |
|
$ 100,000 to $499,000 |
$ 350.00 + $2.00/1,000 or fraction thereof over 99,000 |
|
$ 500,000 + |
$1,150.00 + $1.00/1,000 or fraction thereof over 499,000 |
Schedule VI
Electrical Permit Fees
|
Residential: | |
|
$ 90.00 |
|
$110.00 |
|
$125.00 |
|
$140.00 |
|
$ 35.00 |
|
$ 40.00 |
|
$ 50.00 |
|
$ 85.00 |
|
$ 65.00 |
|
Commercial: | |
|
$ 50.00 |
|
$ 60.00 |
|
$ 65.00 |
|
$ 70.00 |
|
$ 75.00 |
|
$ 80.00 |
|
$ 80.00 |
|
$ 0.20 |
|
Outlets, Fixtures | |
|
$ 10.00 |
|
$ 15.00 |
|
$ 20.00 |
|
$ 25.00 |
|
$ 25.00 |
|
$ 0.10 |
|
Motors | |
|
$ 0.50 |
|
$ 5.00 |
|
Miscellaneous | |
|
$ 40.00 |
|
$ 40.00 |
|
$ 35.00 |
|
$ 10.00 |
|
$ 10.00 |
|
$ 5.00 |
|
$ 5.00 |
|
$ 20.00 |
|
$ 10.00 |
|
$ 0 .50 |
|
Load Control Device |
$ 5.00 |
|
$ 50.00 |
|
$ 50.00 |
|
$ 50.00 |
|
$ 30.00 |
|
$ 40.00 |
|
$ 10.00 |
|
$ 40.00 |
|
Electric Heat
|
$ 0.50 |
Schedule VII
Mechanical Permit Fees
|
Residential | |
|
New Construction Heating Only (1st Unit)
|
$60.00 $30.00 |
|
New Construction Heating and AC (Per Unit)
|
$65.00 $30.00 |
|
Existing Heat Producing Equipment: | |
| |
|
$30.00 |
|
$35.00 |
|
$45.00 |
|
$15.00 |
|
Existing Construction - A/C and Heat Pumps (Per Unit) |
$30.00 |
|
Existing Construction - Complete Heat Pump System |
$45.00 |
|
Gas Connections:
|
$12.00 |
|
Commercial | |
|
Heat Producing Equipment:
|
|
|
$ 35.00 |
|
$ 40.00 |
|
$ 45.00 |
|
$ 15.00 |
|
Air Conditioners, Heat Pumps | |
|
$ 30.00 |
|
$ 45.00 |
|
$ 55.00 |
|
$ 15.00 |
|
$100.00 |
|
Duct System Only |
$40.00 |
|
Water Cooling Towers |
$50.00 |
|
Fan Coil Units, Non Heat Air Handling Units, Non Heat VAV Boxes | |
|
$10.00 |
|
$15.00 |
|
$25.00 |
|
$10.00 |
|
Exhaust Systems for Cooking Equipment |
$50.00 |
|
Paint Spray Booth |
$50.00 |
|
Blower and Exhaust Systems for Dust, Stock, Flammable and Non Flammable Vapor Removal Systems and Conveying, Including Bathroom Exhaust Fans | |
|
$10.00 |
|
$20.00 |
|
$35.00 |
|
Gas Connections: |
|
Schedule VIII
Plumbing Permit Fees
|
Item |
Cost per fixture |
|---|---|
|
Closets |
$7.00 |
|
Showers |
$7.00 |
|
Water Heaters |
$7.00 |
|
Sewer Line per 100 ft. or part thereof |
$7.00 |
|
Water Line per 100 ft. or part thereof |
$7.00 |
|
Water & Sewer in same ditch per 100 ft or part thereof |
$7.00 |
|
Lavatories |
$7.00 |
|
Tubs |
$7.00 |
|
Urinals |
$7.00 |
|
Roof Drains |
$7.00 |
|
Washing Machines |
$7.00 |
|
Slop Sink |
$7.00 |
|
Sinks |
$7.00 |
|
Floor Drains |
$7.00 |
|
Water Coolers |
$7.00 |
|
Storm Drains |
$7.00 |
|
Sewer Lifts |
$7.00 |
|
Dishwashers |
$7.00 |
|
Pits |
$7.00 |
|
Miscellaneous |
$7.00 |
|
Slab Construction |
$40.00 |
ATTEST:
s/Lisa B. Vierling
Lisa B. Vierling, CMC